WORLD'S LARGEST DAM: Three Gorges Dam, CHINA



The Three Gorges Dam is a hydroelectric dam that spans the Yangtze River by the town of Sandouping, located in Yiling District, Yichang, Hubeiprovince, China. The Three Gorges Dam is the world's largest power station in terms of installed capacity (22,500 MW). In 2012, the amount of electricity the dam generated was similar to the amount generated by the Itaipu Dam. 
Except for a ship lift, the dam project was completed and fully functional as of July 4, 2012, when the last of the main turbines in the underground plant began production. Each main turbine has a capacity of 700 MW. The dam body was completed in 2006. Coupling the dam's 32 main turbines with two smaller generators (50 MW each) to power the plant itself, the total electric generating capacity of the dam is 22,500 MW.
As well as producing electricity, the dam is intended to increase the Yangtze River's shipping capacity and reduce the potential for floods downstream by providing flood storage space. The Chinese government regards the project as a historic engineering, social and economic success, with the design of state-of-the-art large turbines, and a move toward limiting greenhouse gas emissions. However, the dam flooded archaeological and cultural sites and displaced some 1.3 million people, and is causing significant ecological changes, including an increased risk of landslides. The dam has been a controversial topic both domestically and abroad

A large dam across the Yangtze River was originally envisioned by Sun Yat-sen in The International Development of China, in 1919. He stated that a dam capable of generating 30 million horsepower (22 GW) was possible downstream of the Three Gorges. In 1932, the Nationalist government, led by Chiang Kai-shek, began preliminary work on plans in the Three Gorges. In 1939, Japanese military forces occupied Yichang and surveyed the area. A design, the Otani plan, was completed for the dam in anticipation of a Japanese victory over China.
In 1944, the United States Bureau of Reclamation chief design engineer, John L. Savage, surveyed the area and drew up a dam proposal for the 'Yangtze River Project'. Some 54 Chinese engineers went to the U.S. for training. The original plans called for the dam to employ a unique method for moving ships; the ships would move into locks located at the lower and upper ends of the dam and then cranes with cables would move the ships from one lock to the next. In the case of smaller water craft, groups of craft would be lifted together for efficiency. It is not known whether this solution was considered for its water-saving performance or because the engineers thought the difference in height between the river above and below the dam too great for alternative methods. Some exploration, survey, economic study, and design work was done, but the government, in the midst of the Chinese Civil War, halted work in 1947.
After the 1949 Communist takeover, Mao Zedong supported the project, but began the Gezhouba Dam project nearby first, and economic problems including the Great Leap Forward and the Cultural Revolution slowed progress. After the 1954 Yangtze River Floods, in 1956, Mao Zedong authored "Swimming", a poem about his fascination with a dam on the Yangtze River. In 1958, after the Hundred Flowers Campaign, some engineers who spoke out against the project were imprisoned.
During the 1980s, the idea of a dam reemerged. The National People's Congress approved the dam in 1992: out of 2,633 delegates, 1,767 voted in favour, 177 voted against, 664 forfeited, and 25 members did not vote. Construction started on December 14, 1994. The dam was expected to be fully operational in 2009, but additional projects, such as the underground power plant with six additional generators, delayed full operation until May 2012. The ship lift is expected to be completed in 2014. The dam had raised the water level in the reservoir to 172.5 m (566 ft) above sea level by the end of 2008 and the designed maximum level of 175 m (574 ft) by October 2010

Generating Capacity

Power generation is managed by China Yangtze Power, a listed subsidiary of China Three Gorges Corporation (CTGC) — a Central Enterprise SOE administered by SASAC. The Three Gorges Dam is the world's largest capacity hydroelectric power station with 34 generators: 32 main generators, each with a capacity of 700 MW, and two plant power generators, each with capacity of 50 MW, making a total capacity of 22,500 MW. Among those 32 main generators, 14 are installed in the north side of the dam, 12 in the south side, and the remaining six in the underground power plant in the mountain south of the dam. The expected annual electricity generation will be over 100 TWh.

Generators

The main generators weigh about 6,000 tonnes each and are designed to produce more than 700 MW of power. The designed head of the generator is 80.6 meters (264 ft). The flow rate varies between 600–950 cubic metres per second (21,000–34,000 cu ft/s) depending on the head available. The greater the head, the less water needed to reach full power. Three Gorges uses Francis turbines. Turbine diameter is 9.7/10.4 m (VGS design/Alstom's design) and rotation speed is 75 revolutions per minute. Rated power is 778 MVA, with a maximum of 840 MVA and a power factor of 0.9. The generator produces electrical power at 20  kV. The outer diameter of the generator stator is 21.4/20.9 m. The inner diameter is 18.5/18.8 m. The stator, the biggest of its kind, is 3.1/3 m in height. Bearing load is 5050/5500 tonnes. Average efficiency is over 94%, and reaches 96.5%.

Three Gorges Dam Francis turbine
The generators are manufactured by two joint ventures. One of them includes Alstom, ABB Group, Kvaerner, and the Chesine company Haerbin Motor. The other includes Voith, General Electric, Siemens (abbreviated as VGS), and the Chinese company Oriental Motor. The technology transfer agreement was signed together with the contract. Most of the generators are water-cooled. Some newer ones are air-cooled, which are simpler in design and manufacture and are easier to maintain


The 14 north side main generators are in operation. The first (No. 2) started on July 10, 2003. The north side became completely operational September 7, 2005 with the implementation of generator No. 9. Full power (9,800 MW) was only reached on October 18, 2006 after the water level reached 156 m.
The 12 south side main generators are also in operation. No.22 began operation on June 11, 2007 and No. 15 started up on October 30, 2008. The sixth (No. 17) began operation on December 18, 2007, raising capacity to 14.1 GW, finally surpassing Ita (14.0 GW), to become the world's largest hydropower plant by capacity.
The 6 underground main generators are also in operation as of May 23, 2012, when the last main generator, No. 27, finished its final test. raising capacity to 22.5 GW. After 9 years of construction, installation and testing, the power plant is now fully operational